πŸ”‹ Standalone BESS β€” Co-Development

BESS Cerignola

Cerignola, Province of Foggia β€” Puglia, Italy

Early Development Co-Development Opportunity MACSE / Merchant COD 2027/28
100 MW
Power Capacity
400–640 MWh
Energy Capacity
8.8–10.0%
Target Project IRR
€2.5M
Total Co-Dev. Fee
Project Summary

BESS Cerignola β€” 100 MW | 400/640 MWh, Puglia

Co-Development Opportunity. This project is offered as a co-development transaction: land and grid connection have been secured. Permitting has not yet been submitted. The investor can configure the project according to their own BESS blueprint. Studio Santi Engineering S.r.l. acts as sole developer and technical advisor.

The BESS Cerignola project is a 100 MW standalone Battery Energy Storage System located in the municipality of Cerignola, Province of Foggia, in Puglia β€” the most photovoltaic-dense region in Italy. The province of Foggia alone had over 21.7 GW of grid connection requests for new solar PV plants as of November 2025, creating a structural and urgent need for large-scale storage infrastructure to balance the grid.

The project is being developed by Studio Santi Engineering S.r.l., an Italian energy engineering consultancy with 30 specialist engineers, a 25-year track record in the Italian energy market, and a demonstrated pipeline of approximately 1.2 GW in renewable energy plants and 700 MW / 5 GWh in energy storage systems. The firm is directed by Dr. Federico Santi, PE β€” professor of Energy System Analysis and Modeling at Sapienza University of Rome and board member of the Italian Association for Energy Economics.

The project is offered in two alternative configurations: a 4-hour scenario (100 MW | 400 MWh) optimised for merchant markets and ancillary services, or a 6.4-hour scenario (100 MW | 640 MWh) designed for participation in the Italian MACSE mechanism β€” a state de-risking programme supporting the development of 50 GWh of new BESS capacity in Italy. The two scenarios are interchangeable at container level without requiring changes to the authorisation.

The total site area is 2.1 hectares of perfectly flat agricultural land in the Tavoliere delle Puglie plain. Letters of intent have been signed with the land owners for a purchase (not a lease) upon obtaining all required authorisations. The Minimum General Technical Solution (STMG No. 202501261) for grid connection was issued by Terna S.p.A. in June 2025, reviewed in November 2025, with acceptance deadline set for March 2026.

Power Capacity
100 MW
Both injection and withdrawal
Energy Capacity
400 / 640 MWh
4h or 6.4h duration (two scenarios)
Project Type
Stand-alone
No co-location with generation asset
Grid Connection
36 kV / 3 km
STMG No. 202501261 issued by Terna
Land
2.1 hectares
Ownership (LOIs signed); flat terrain
Developer
Studio Santi
Studio Santi Engineering S.r.l., Rome
Technical Specifications

Plant Design & Site Data

The BESS Cerignola plant uses a modular containerised architecture compliant with current market standards: each Power Conversion System (PCS) unit is a 5 MVA / 20ft container, and each battery unit is a 20ft container rated at either 5 MWh (400 MWh scenario) or 8 MWh (640 MWh scenario). The design fully complies with the Italian Fire Brigade Guideline No. 21021 of 23/12/2024, which defines the maximum allowable energy density per fire compartment. The 640 MWh configuration is achieved by simply substituting the 5 MWh containers with 8 MWh units β€” with no impact on the authorisation perimeter.

The site sits on the Tavoliere delle Puglie plain, characterised by Quaternary alluvial sediments offering optimal geotechnical conditions: perfectly flat terrain, good soil bearing capacity, and favourable electrical impedance. The total site is divided into two lots β€” Lotto A (1.23 ha, 45 islands, 180 MWh / 288 MWh) and Lotto B (0.87 ha, 55 islands, 220 MWh / 352 MWh) β€” for a combined footprint of 2.10 ha. The plant connects via an underground 36 kV cable approximately 3 km long, running entirely along public roads, to a new 380/220/36 kV electrical substation being built by Terna on a LILO (line-in line-out) basis along the 380 kV Andria–Manfredonia power transmission line. No expropriation is required. The investor retains full flexibility over hardware and software solutions β€” no OEM exclusivity is imposed.

Power (MW)
100 MW
Max per STMG, both injection & withdrawal
Capacity β€” Scenario A
400 MWh
4h | 5 MWh containers | Merchant optimised
Capacity β€” Scenario B
640 MWh
6.4h | 8 MWh containers | MACSE optimised
Container Type
20ft Modular
5 MVA PCS + 5 or 8 MWh BESS per unit
Connection Voltage
36 kV
New 380/220/36 kV Terna substation
STMG Reference
202501261
Issued June 2025, revised Nov. 2025
Cable Length
~3 km
Underground, along public roads
Site Area
2.1 ha
Lotto A (1.23 ha) + Lotto B (0.87 ha)
Ground Conditions
Optimal
Flat alluvial plain, good impedance
OEM Flexibility: The project specification imposes no exclusivity regarding hardware or software solutions. The investor is free to select their preferred BESS supplier, PCS manufacturer, and SCADA/EMS platform. Studio Santi can provide owner's engineering support for vendor selection, technical due diligence, and EPC tendering.
Financial Structure & Returns

Investment Scenarios & Co-Development Economics

The project is structured as a co-development transaction, with the total co-development fee set at €25,000/MW β€” €2.5 million in total β€” payable in four tranches tied to permitting and construction milestones. The investor participates from an early stage (Q1 2026) and accompanies the project through to Ready-to-Build, retaining the option to either hold the project through to COD or execute a pre-construction exit. Based on average Italian BESS transaction values for 2024–2025 (10–15% of investment cost), the estimated pre-construction market value ranges from €5.1M to €10.9M depending on the capacity scenario, implying an exit gross profit of 2.5x to 5.0x the co-development fee.

Two revenue scenarios are available. The Merchant scenario (400 MWh) targets participation in the Italian Day-Ahead, Intraday, and ancillary services markets (MSD), generating estimated revenues of €8.0M/year and a project IRR of 10.0%. The MACSE scenario (640 MWh) leverages Italy's de-risking mechanism for energy storage β€” a state-backed support scheme targeting 50 GWh of new BESS capacity β€” with an estimated MACSE fee of approximately 13 k€/kWh/year, reducing merchant exposure significantly and yielding a project IRR of 8.8% on a total investment of €72.7M. Hybrid configurations combining MACSE capacity reservation with residual merchant exposure are also feasible. The MACSE fee can alternatively be replaced by an equivalent tolling agreement with an energy company.

Scenario A β€” Merchant
100 MW | 400 MWh | 4 hours
€50.7M
Total CAPEX
€8.0M/y
Est. Revenue
10.0%
Project IRR

Optimised for Day-Ahead, Intraday, and ancillary services markets. Higher revenue upside, higher merchant price risk. Suitable for investors comfortable with Italian power market exposure.

Co-Development Payment Schedule

The total co-development fee of €2,500,000 (€25,000/MW) is paid in four tranches, each tied to a defined project milestone. If the project fails to reach Ready-to-Build, the advance payments are partially refunded to cover only actual development expenses incurred.

Milestone Timing €/MW Total (€) % of Total
STMG Acceptance + Preliminary Land Agreement Q1 2026 8,500 850,000 34%
AU Filing at Puglia Region (after Terna Benestare) Q4 2026 2,500 250,000 10%
AU Release + Consolidation (4 months after AU) Q3–Q4 2027 12,500 1,250,000 50%
Grid-Related Capital Expenditure / COD Q2–Q3 2028 1,500 150,000 6%
Total 25,000 2,500,000 100%
Pre-Construction Exit Values
Scenario A β€” Pre-Constr. Value
€5.1 – 7.6M
10–15% of €50.7M investment; avg. 2024–2025
Scenario B β€” Pre-Constr. Value
€7.3 – 10.9M
10–15% of €72.7M investment; avg. 2024–2025
Exit Gross Profit
€3 – 8M
2.5x – 5.0x co-development fees
[Inferenza] Financial projections (CAPEX, revenues, IRR) are sourced directly from the Studio Santi teaser (December 2025 / January 2026). They represent indicative estimates based on preliminary design and market assumptions. No independent financial model audit has been performed at this stage. Figures should be verified by an independent financial advisor before any investment decision. DSCR, debt/equity structure, and financing terms are not confirmed at this stage β€” Studio Santi notes that project financing support with leading Italian banks is available.
Risk Assessment

Co-Development Risk Profile

Given the project's early-stage status, the risk profile differs from a Ready-to-Build asset. The key risks are concentrated in the permitting phase and revenue model selection. The developer has structured the co-development agreement to partially absorb downside risk: if the project fails to reach Ready-to-Build, advance payments are refunded net of actual development expenses incurred. The following matrix reflects a post-mitigation assessment at the co-development entry stage.

Risk Category Risk Description Rating Mitigation
Permitting Risk Delay or rejection of AU or Terna Benestare Medium BESS classified as public utility works; Studio Santi has strong TSO/DSO relationships and 25yr Italian regulatory track record
STMG Acceptance Risk Failure to accept STMG within March 2026 deadline Low STMG already issued and revised; acceptance is a commercial decision within investor's control once agreed
Land Risk Owner withdraws from sale prior to permit Low LOIs signed; preliminary notarial contracts executed at STMG acceptance; Italian law provides expropriation route if needed
Merchant Price Risk Italian power prices below model assumption (Scenario A) Medium Mitigated by Scenario B (MACSE) or hybrid approach; MACSE provides long-term contracted revenue floor
MACSE Mechanism Risk MACSE auction delayed or not awarded (Scenario B) Medium MACSE 2027 auction anticipated; fallback to merchant or equivalent tolling agreement with energy company
Technology Risk Container technology obsolescence or supply delay Low No OEM exclusivity; investor selects preferred supplier; modular design allows phased procurement
Grid Connection Risk Terna substation construction delay Medium Substation under construction by Terna (TSO obligation); delay impacts COD but not authorisation
Co-Dev Capital at Risk Project fails to reach RtB; advance payments lost Low Contractual refund mechanism: advance payments returned net of actual development costs incurred
Regulatory Risk Changes to Italian energy storage regulation Low Studio Santi Director contributed to Italian energy regulation development; strong regulatory intelligence and early-warning capability
Development & Construction Schedule

Project Milestones

The project follows a two-year development path from transaction initiation to Ready-to-Build, with COD targeted for 2027/28. The timeline is partly contingent on the MACSE auction schedule β€” if the investor targets MACSE participation, COD alignment with the 2027 auction round may influence the construction start decision.

June 2025
STMG Issued by Terna S.p.A.
Minimum General Technical Solution No. 202501261 issued for 100 MW BESS grid connection at 36 kV to the new 380/220/36 kV substation on the Andria–Manfredonia line
November 2025
STMG Revised
Updated STMG issued by Terna with revised technical conditions. Acceptance deadline confirmed for March 2026.
December 2025 / January 2026
Co-Development Teaser Issued
Studio Santi publishes co-development teaser to qualified investors. Transaction initiated.
Q1 2026 β€” Current
STMG Acceptance + Preliminary Land Agreements
Investor accepts STMG (deadline March 2026). Initial advance payment: €850,000 (€8,500/MW). Preliminary notarial land purchase contracts signed with owners.
2026 (during year)
Engineering Design & Permitting Preparation
Full technical design produced in line with investor's BESS blueprint. Terna Benestare application submitted. AU application documentation prepared.
Q4 2026
AU Filed at Puglia Region
Autorizzazione Unica application submitted under D.Lgs. 190/2024. Follow-up advance payment: €250,000 (€2,500/MW).
Q3–Q4 2027
AU Released β†’ Ready-to-Build
Autorizzazione Unica issued by Puglia Region. 4-month consolidation period begins. Development premium: €1,250,000 (€12,500/MW). Land ownership finalised. Project is Ready-to-Build.
Q2–Q3 2028
Commercial Operation Date (COD)
Grid energisation and commissioning. COD timing may be influenced by MACSE 2027 auction strategy. Grid CapEx payment: €150,000. Revenue generation begins.
MACSE Strategy Note: The MACSE 2027 auction β€” Italy's de-risking mechanism for new BESS development β€” may influence the optimal COD target. If the investor chooses the 640 MWh / 6.4h MACSE scenario, the construction schedule should be aligned to qualify for the 2027 auction round. Studio Santi can advise on auction strategy and submission requirements.

Request the full project package

Detailed technical documentation, financial model, layout drawings, and STMG documentation are available to credentialed investors under NDA. Studio Santi Engineering S.r.l. manages all investor communications directly.

Request NDA & Documents β†’
← Back to All Projects Interested? Contact Us β†’