โ˜€๏ธ Solar PV (Tracker) โ€” PPA Signed โ€” Financing Sought

Camelzone Solar

Sans Souci Farm, Mashava, Masvingo Province โ€” Zimbabwe

60 MWp / 50 MWac โ€” Single-Axis Tracker PPA Signed โ€” ZETDC 25yr USD 64M Financing Sought Zimbabwe โ€” Africa
60 MWp
Installed DC Capacity
$0.0895/kWh
PPA Tariff โ€” ZERA Approved
15.48%
Project IRR (Developer Model)
USD 64M
Total Financing Required
โœ…
PPA Signed and Generation Licence Issued. This project has achieved two of the most critical milestones in the African IPP development process: a 25-year take-or-pay Power Purchase Agreement (PPA) with ZETDC at US$0.0895/kWh (ZERA Board-approved 20 July 2021), and a ZERA Generation Licence (GC0108/2020) valid until 2 October 2045. The Grid Impact Assessment is approved for up to 100 MWac. The outstanding critical path item is USD 64 million in financing โ€” the only major unlock required to commence construction and reach the targeted SCOD of 31 December 2026.
Project Summary

Bankable Solar IPP โ€” PPA and Licence in Hand

Camelzone Solar is a 60 MWp DC / 50 MW AC ground-mounted photovoltaic IPP being developed by Camelzone Enterprises (Pvt) Ltd (trading as Camel Energy) at Sans Souci Farm, Mshandike resettlement, approximately 6 km west of Mashava town in Masvingo Province, Zimbabwe. The 165-hectare project site is situated in one of Zimbabwe's highest-irradiation provinces, with single-axis horizontal trackers providing the technology backbone. The project is scalable to 100 MW AC in a second phase, and the Grid Impact Assessment (GIA) has already been approved for this full 100 MWac capacity, securing grid access for future expansion without requiring a new grid study.

What distinguishes Camelzone Solar from most sub-Saharan African solar projects at a similar stage of development is the combination of a signed, ZERA-approved 25-year take-or-pay PPA with the Zimbabwe Electricity Transmission and Distribution Company (ZETDC), and a ZERA Generation Licence (GC0108/2020) valid until 2 October 2045. Both instruments are in place. The project is also uniquely advantaged by its grid connection geometry: the Tokwe 132kV substation operated by ZETDC is located less than 500 metres from the plant boundary โ€” an exceptionally short connection distance that reduces transmission line costs to an estimated USD 3.792 million and minimises technical losses.

PPA Signed 25-Year Take-or-Pay with ZETDC at US$0.0895/kWh
The PPA between Camelzone Enterprises (Seller) and the Zimbabwe Electricity Transmission and Distribution Company (Buyer) defines a 25-year contracted offtake at USD 0.0895/kWh, with an expiry date of 2 October 2045. The tariff was formally approved by the ZERA Board on 20 July 2021. The agreement operates on a take-or-pay basis โ€” ZETDC is contractually obligated to purchase up to the full contracted capacity of 50 MW AC, with Deemed Energy Payment provisions protecting the project from grid-side curtailment events caused by buyer default. The tariff of 8.95 US cents/kWh represents a strong margin over the developer's modelled LCOE of 3.50 US cents/kWh, generating an implicit margin of 5.45 US cents/kWh (155.52%). At modelled Year 1 revenue of USD 12.31 million, the project's debt service capacity is materially robust, subject to independent verification of the financial model.
Contracted Capacity
50 MW AC
Scalable to 100 MW AC โ€” GIA approved for full capacity
PPA Tariff
US$0.0895/kWh
ZERA Board approved 20 Jul 2021 โ€” 25-year take-or-pay
Generation Licence
GC0108/2020
ZERA โ€” issued 2 Oct 2020, valid 25 years to 2 Oct 2045
Project Location
Mashava, Masvingo
165 ha โ€” 6 km west of Mashava town, Zimbabwe
Grid Connection
<500m to 132kV
Tokwe 132kV ZETDC Substation โ€” connection cost USD 3.792M
Target SCOD
31 Dec 2026
~9 months construction from financing โ€” China Energy EPC
Zimbabwe Energy Context. Zimbabwe faces a chronic electricity deficit, with demand regularly outstripping supply from the ageing Kariba South hydroelectric plant and the Hwange thermal station. Load-shedding of 12โ€“18 hours per day has been reported in recent years. The government's stated priority is to urgently add 2,000 MW of new generating capacity, with solar PV as the preferred technology given Zimbabwe's high solar irradiation profile (GHI above 2,000 kWh/mยฒ/year across Masvingo Province). This structural demand deficit creates strong policy support and payment obligation urgency for the ZETDC offtaker.
Technical Specifications

Plant Design, Equipment & Grid Integration

The Camelzone Solar plant is designed as a ground-mounted utility-scale installation using single-axis horizontal trackers (SAT) with Longi Solar LR5-72HBD-540M modules โ€” a high-efficiency bifacial half-cut PERC module rated at 540W per panel. Single-axis trackers at the latitude of Masvingo (~20ยฐS) provide meaningful yield uplift versus fixed-tilt, improving energy output during morning and afternoon hours and increasing the plant's daily generation window. The total installed DC peak power is 60.03 MWp, connected to 228 Sungrow SG250HX-IN-20 string inverters with a combined nominal AC output of 50,160 kVA (50.16 MW AC), establishing the contracted capacity of 50 MW AC with ZETDC.

The project's most significant technical advantage is its proximity to the national grid. The ZETDC Tokwe 132kV Substation is located less than 500 metres from the plant boundary โ€” an exceptionally short connection distance for a project of this scale in sub-Saharan Africa. The recommended grid connection scope consists of: 5 km of new 132kV single-circuit transmission line and two 132kV line bays (one at the plant step-up substation and one at Tokwe Substation), estimated at USD 3.792 million. The Grid Impact Assessment (GIA), conducted by the ZETDC System Development Division in May 2016, has been approved for the connection of up to 100 MWac โ€” covering both Phase 1 and the planned Phase 2 expansion without requiring a repeat grid study.

DC Capacity (STC)
60.03 MWp
Nominal DC power at Standard Test Conditions
AC Contracted Capacity
50 MW AC
Scalable to 100 MW AC Phase 2 โ€” GIA already approved
PV Modules
Longi LR5-72HBD-540M
540W bifacial half-cut PERC โ€” Tier 1 manufacturer
Inverters
228 ร— Sungrow SG250HX
Total nominal AC: 50,160 kVA โ€” DC/AC ratio: 1.197
Tracking System
Single-Axis Tracker
Horizontal SAT โ€” maximises yield at 20ยฐS latitude
Site Area
165 ha
Sans Souci Farm โ€” state land, provisional offer letter held
Grid Connection Distance
<500 m
Tokwe 132kV Substation โ€” exceptionally short connection
Grid Connection Voltage
132 kV
5km 132kV single-circuit line + two line bays
Grid Connection Cost
USD 3.792M
Included within total USD 64M financing requirement
[Non verificato] โ€” Independent Energy Yield Assessment Not Disclosed. No independent P50/P90 energy yield study has been referenced in the available investment memorandum. The developer's financial model is based on assumed yield parameters, but a bankable energy yield assessment (EYA) from an accredited independent engineer (DNV, Solargis, 3E, or equivalent) is a standard requirement for project finance lenders at Financial Close. The Masvingo Province location (approximately 20ยฐS, altitude ~1,000m) is well-served by global irradiation databases and should support a high-quality EYA. Based on GHI data for the region (approximately 2,000โ€“2,100 kWh/mยฒ/year), a 60 MWp tracker plant would be expected to generate approximately 110,000โ€“120,000 MWh/year [Inferenza] โ€” implying a P50 specific yield of roughly 1,830โ€“2,000 kWh/kWp/year, consistent with the high-irradiation savanna environment.
Financial Structure & Developer Model

USD 64M Financing Required โ€” 15.48% IRR (Developer Projection)

The developer's draft financial model, as presented in the investment memorandum, projects strong profitability metrics anchored by the USD 0.0895/kWh PPA tariff and a modelled LCOE of USD 0.0350/kWh โ€” implying a margin of 5.45 US cents/kWh (155.52%). Year 1 revenue is projected at USD 12.31 million, with a project-level IRR of 15.48% and a net present value of USD 105.2 million on a USD 64 million total investment. The installed cost per kWp is stated at USD 1,100/kWp, implying a total EPC cost of approximately USD 66 million โ€” suggesting the USD 64 million financing figure may be a slightly compressed estimate, or that the developer is contributing equity to bridge the gap. Investors should request the complete financial model, including assumptions on discount rate, degradation, O&M costs, debt service structure, and currency treatment.

Financial MetricValue (Developer Model)Notes
Total Financing RequiredUSD 64,000,000Debt + equity โ€” structure to be defined with investors
Installed CostUSD 1,100/kWpImplies ~USD 66M total EPC cost at 60.03 MWp [Inferenza]
Year 1 RevenueUSD 12,313,373Based on PPA tariff ร— contracted energy volume
Project IRR15.48%[Non verificato] โ€” developer draft model, not independently audited
Net Present Value (NPV)USD 105,205,162[Non verificato] โ€” discount rate assumption not disclosed
LCOEUSD 0.035/kWh (3.50 ยข)[Non verificato] โ€” developer model; no independent verification
PPA Tariff Margin5.45 ยข/kWh (155.52%)PPA tariff 8.95 ยข minus LCOE 3.50 ยข
PPA Tariff (ZERA Approved)USD 0.0895/kWh25-year take-or-pay โ€” ZERA Board approved 20 Jul 2021
[Non verificato] โ€” Financial Model Is Developer Draft. All financial metrics above are sourced from the developer's own draft financial model. No independent financial audit, lender's report, or third-party cost verification has been performed. In particular: (1) the LCOE of 3.50 ยข/kWh and the IRR of 15.48% are based on unverified cost and yield assumptions; (2) the NPV discount rate is not disclosed; (3) the installed cost of USD 1,100/kWp is above current market benchmarks for utility-scale tracker systems in southern Africa (typically USD 650โ€“900/kWp in 2025โ€“2026 procurement), which should be interrogated; (4) O&M cost assumptions, debt structure, equity split, and DSCR covenant are not disclosed. Investors must commission an independent technical advisor and financial model audit before committing capital.
Foreign Currency Convertibility Note. The PPA tariff is denominated in USD, which aligns with equipment procurement costs. However, the outstanding Government Implementation Agreement (GIA) โ€” which requires an RBZ (Reserve Bank of Zimbabwe) Undertaking for Foreign Currency Convertibility and Transfer โ€” is a critical pre-condition for investment. Zimbabwe has historically experienced significant foreign currency rationing and US dollar transfer restrictions. Confirmation of the RBZ undertaking as part of the GIA package is essential for any foreign equity or debt investor evaluating this project. DFI participation (AfDB, DFC/OPIC, MIGA insurance) is strongly advisable to mitigate foreign currency and convertibility risk.
Risk Assessment

Project Risk Profile

The Camelzone project's risk profile is shaped by an unusual combination: an exceptionally strong commercial foundation (signed PPA, issued licence, approved GIA, exceptional grid proximity), alongside a set of pre-Financial Close gaps that must be resolved before capital can be committed. The primary risks are institutional and sovereign rather than technical or commercial: ZETDC payment capacity, the outstanding Government Implementation Agreement and RBZ forex undertaking, land lease formalisation, and the incomplete EIA and resettlement process are the four items that will determine whether lenders and equity investors can proceed.

Risk CategoryDescriptionRatingMitigation
Commercial Foundation โ€” PPA & Licence 25-year take-or-pay PPA signed at 8.95 ยข/kWh (ZERA approved). Generation Licence issued. GIA approved for 100 MWac. These are confirmed, signed instruments. Strong Positive No mitigation needed โ€” these are the project's strongest bankability credentials. Verify executed document originals and ZERA licence register confirmation.
ZETDC Payment Risk / Creditworthiness ZETDC is a state-owned utility in a country with a history of energy sector fiscal stress. Payment delays or defaults by ZETDC are a credible risk, particularly given Zimbabwe's foreign currency constraints. High Government Implementation Agreement (GIA) with sovereign guarantee and RBZ forex undertaking is the standard mitigation. MIGA political risk insurance and/or DFI participation (AfDB, IFC, DFC) are essential for lender comfort. PPA Deemed Energy Payment provisions protect against curtailment-related non-payment.
Government Implementation Agreement (GIA) Outstanding The GIA โ€” including the Project Development Support Agreement and the RBZ Undertaking for forex convertibility and repatriation โ€” has not yet been finalised. Without it, no foreign equity or debt investor can confidently repatriate returns. High โ€” Critical Path Confirm GIA negotiation status, responsible ministry counterpart, and timeline to execution as the first diligence priority. GIA finalisation typically requires government legal counsel, treasury, and central bank alignment and can take 12โ€“24 months.
Land Lease Formalisation The project holds only a provisional offer letter for the 165 ha state land. The substantive long-term lease will only be issued once development commences โ€” creating a chicken-and-egg dependency with investor commitment. Medium Negotiate a binding land undertaking from the Ministry of Lands conditional on Financial Close rather than commencement of construction. Confirm lease term aligns with PPA tenor (25 years). Lenders require a confirmed leasehold or legal opinion on priority of land rights before Financial Close.
EIA โ€” Full Report Outstanding Only an EIA Prospectus (June 2019) has been prepared. A full EIA report and approval from EMA (Environmental Management Authority of Zimbabwe) is required before construction can commence. The EIA process in Zimbabwe typically takes 12โ€“18 months. Medium Commission the full EIA immediately using an EMA-accredited consultant. Begin the EIA process in parallel with GIA and financing negotiations to avoid sequential timeline compression. IFC PS1 and PS3 (biodiversity) standards should be integrated into the EIA scope if DFI participation is targeted.
Resettlement of 19โ€“20 Families Physical relocation of rural families from the site has not yet been executed. Under IFC Performance Standard 5, lenders require a complete Resettlement Action Plan and substantially complete resettlement before construction commences. Medium Commission a full RAP compliant with IFC PS5 and the World Bank OP 4.12. Engage independent social consultant for community liaison, grievance mechanism establishment, and livelihood restoration planning. Timeline: 12โ€“18 months from commission to completion.
Financial Model Not Independently Verified The 15.48% IRR and USD 105M NPV are developer draft projections. The USD 1,100/kWp installed cost is above current market benchmarks for tracker installations in the region. Key assumptions (yield, degradation, O&M, debt structure) are not disclosed. High โ€” Unverified Commission independent technical and financial model audit from qualified advisor (e.g., PwC, KPMG, Mott MacDonald, DNV) as a condition of any indicative term sheet. Focus specifically on installed cost benchmark, energy yield verification, and DSCR sensitivity analysis.
Zimbabwe Sovereign Risk Zimbabwe has experienced hyperinflation, currency reform, and political instability. Despite improvement since 2018, country risk remains elevated with a history of difficulty for foreign investors repatriating capital and returns. High GIA with RBZ undertaking is the principal structural mitigation. MIGA PRI insurance covers transfer restriction, expropriation, and political violence risks. DFI co-investor participation provides deterrence. USD-denominated PPA protects against currency mismatch at the project level.
Grid Connection Proximity The Tokwe 132kV substation is less than 500m from the site โ€” a materially positive technical factor that reduces connection cost, technical losses, and right-of-way acquisition complexity. Strong Positive Confirm substation available capacity for 50 MW injection via TCA negotiation. Phase 2 expansion to 100 MW already GIA-approved, which is a valuable optionality for investors targeting a second close.
Development Timeline

From Financing to Commercial Operations โ€” SCOD 31 Dec 2026

January 2007
Company Incorporation
Camelzone Enterprises (Pvt) Ltd incorporated under the Companies Act [Chapter 24:03] on 26 January 2007. Current shareholding: Adwell Farai Lazarus Rukanda and Rudo Ruvheneko Rukanda.
May 2016
Grid Impact Assessment Approved for 100 MWac
ZETDC System Development Division conducts and approves the Grid Impact Assessment for connection of up to 100 MWac at the Tokwe 132kV Substation. This is a critical bankability milestone: the GIA covers both Phase 1 (50 MW) and Phase 2 (100 MW) expansion without requiring a repeat study.
June 2019
EIA Prospectus Prepared
Hazwin Consultancy prepares the Environmental Impact Assessment Prospectus under the Environmental Management Act 20:27 of 2002. Community awareness exercise conducted with 19โ€“20 affected rural families; families agree in principle to relocation to an adjacent Ministry-provided site. Note: this is the prospectus only โ€” the full EIA report is still required.
2 October 2020
ZERA Generation Licence Issued โ€” GC0108/2020
Zimbabwe Energy Regulatory Authority issues Generation Licence GC0108/2020 to Camelzone Enterprises (Pvt) Ltd. The licence covers 25 years and is valid until 2 October 2045. This is a confirmed, issued instrument on record with ZERA.
20 July 2021
PPA Tariff Approved by ZERA Board
The ZERA Board formally approves the PPA tariff of USD 0.0895/kWh (8.95 US cents/kWh) for the 25-year take-or-pay offtake arrangement between Camelzone Enterprises (Seller) and ZETDC (Buyer). This tariff approval converts the PPA from a negotiated commercial document into a ZERA-sanctioned regulated instrument.
Completed โ€” Pre-2025
PPA Executed โ€” Provisional EPC Contract with China Energy
25-year take-or-pay PPA executed between Camelzone and ZETDC at USD 0.0895/kWh, expiry 2 October 2045. Provisional EPC Contract signed with China Energy for the plant construction; binding EPC contract to follow at Financial Close with an expected 9-month construction period.
Current Stage โ€” 2025/2026
Financing Mandate โ€” USD 64M Sought
โณ The project is actively seeking USD 64 million in financing (debt and/or equity). Parallel tracks required: (1) Government Implementation Agreement and RBZ forex undertaking finalisation; (2) Transmission Connection Agreement execution with ZETDC; (3) Full EIA completion and EMA approval; (4) Resettlement Action Plan execution; (5) Long-term land lease formalisation. Studio Santi Capital is supporting investor engagement for this opportunity.
Pre-Financial Close
GIA, TCA, Full EIA, RAP and Land Lease Execution
Government Implementation Agreement with sovereign guarantee and RBZ forex undertaking finalised. Transmission Connection Agreement with ZETDC executed. Full EIA report submitted and approved by EMA. Resettlement Action Plan completed and community relocation executed. Long-term land lease issued by Ministry of Lands.
Financial Close
Debt and Equity Closing โ€” EPC Notice to Proceed
All financing tranches committed and closed. Binding EPC contract executed with China Energy with fixed-price, date-certain terms, performance guarantees, and liquidated damages. Notice to Proceed issued. All project agreements effective.
~9 Months Post-Financial Close
Mechanical Completion & Commissioning
228 Sungrow SG250HX inverters, Longi Solar tracker arrays, 132kV step-up substation, and 5km transmission line to Tokwe substation completed and commissioned. ZETDC metering and grid synchronization tests completed.
Target: 31 December 2026
Scheduled Commercial Operations Date (SCOD)
50 MW AC delivered to the ZETDC national grid at Tokwe 132kV Substation. PPA revenue stream commences at USD 0.0895/kWh on a take-or-pay basis. Year 1 revenue projected at USD 12.31 million (developer model โ€” not independently verified). Generation Licence active.
Phase 2 โ€” Post-COD
Expansion to 100 MW AC
The existing GIA approval covers connection of up to 100 MWac, providing a ready pathway for Phase 2 expansion without a repeat grid study. Phase 2 financing and commercial framework to be agreed with investors at or after Financial Close for Phase 1.

Request the Full Investment Package

The complete investment memorandum, PPA, ZERA Generation Licence, Grid Impact Assessment, provisional EPC term sheet, and developer financial model are available to credentialed investors under NDA. Contact Studio Santi Capital to initiate engagement with Camelzone Enterprises.

Express Interest โ†’
โ† Back to All Projects Interested in this project? Contact Us โ†’