β˜€οΈ Solar PV IPP β€” MOZAL Industrial Offtake Opportunity

Boane Solar

Beleluane Industrial Park, Maputo Province β€” Southern Mozambique

30 MWp (up to 50 MWp) BOOT Structure MOZAL 25–40 MW Demand Indicated Mozambique β€” Africa
30 MWp
Installed Capacity (DC)
53,310 MWh
P50 Annual Yield
1,777 kWh/kWp
P50 Specific Yield
25–40 MW
MOZAL Indicated Demand
⚑
Site Relocated β€” MOZAL Industrial Offtake Emerges as Preferred Route. The project was originally planned at the Boane substation at 50 MWp, but EDM's National Power Grid Integration Studies determined that the Boane substation cannot accommodate the planned output. EDM has recommended relocation to the Beleluane Substation, located adjacent to the MOZAL aluminium smelter β€” one of Africa's largest industrial power consumers β€” which has independently indicated demand of 25–40 MW. This creates a materially different commercial pathway from the standard EdM PPA route used for Alto Molocue.
Project Summary

Bilateral IPP Award β€” Industrial Offtake Pivot at Beleluane

The Boane Solar project is a 30 MWp ground-mounted photovoltaic power plant (scalable to 50 MWp) in Maputo Province, Southern Mozambique. Like the Alto Molocue project, it has been awarded to a local private developer by MIREME and ARENE on a bilateral BOOT basis, with Electricidade de MoΓ§ambique (EdM) as the designated offtaker under a 20-year take-and-pay PPA. The 64-hectare site has been secured through a DUAT. However, the Boane project has undergone a significant strategic pivot that distinguishes it from a standard EdM-offtake IPP: during EDM's National Power Grid Integration Studies, the utility determined that the original Boane substation lacks the capacity to accommodate the full planned output, prompting a recommendation to relocate the project to the Beleluane Substation, 6 km from the new site β€” adjacent to the Beleluane Industrial Park in Maputo.

The Beleluane relocation introduces a transformative commercial opportunity: MOZAL β€” the Mozal aluminium smelter joint venture located in Beleluane Industrial Park, one of Southern Africa's largest industrial electricity consumers β€” has indicated interest in purchasing power directly from the project, with an estimated demand of 25 to 40 MW. This creates the possibility of structuring a direct industrial Power Purchase Agreement (C&I PPA or direct-wire arrangement) with MOZAL as the primary or co-offtaker, potentially alongside or instead of the EdM route. An industrial offtake with MOZAL would represent a fundamentally stronger credit counterpart than a standalone EdM PPA, given MOZAL's international ownership structure.

Industrial Offtake MOZAL β€” The Beleluane Opportunity
MOZAL is a large-scale aluminium smelter located in the Beleluane Industrial Park, Matola, Maputo Province β€” a joint venture between South32 (47.1%), Mozambican state interests, and other shareholders. Aluminium smelting is one of the most electricity-intensive industrial processes globally, with MOZAL requiring continuous, reliable baseload power at scale. The plant's indicated demand of 25–40 MW from the Boane Solar project would represent a C&I off-take agreement with a credit counterpart whose corporate structure is fundamentally different from EdM's sovereign credit profile. A direct MOZAL PPA would eliminate or significantly reduce the need for sovereign guarantees and DFI political risk insurance that are otherwise essential for an EdM-only offtake in this credit environment. However, solar PV as an intermittent resource must be evaluated against MOZAL's 24-hour continuous power demand β€” hybrid storage or grid backup arrangements would need to be part of the commercial framework.
Project Name
Boane Solar PV IPP
Bilateral award β€” MIREME & ARENE
Capacity
30 MWp (up to 50)
Scalable β€” subject to Beleluane substation confirmation
Site Area
64 ha
DUAT secured β€” near Beleluane Substation (6 km)
Grid Connection
66 kV β€” 6 km
EDM Southern network β€” Beleluane Substation (relocated)
Primary Offtaker (base)
EdM β€” 20yr PPA
Take-and-pay β€” subject to PPA negotiation and MoF guarantee
Industrial Offtake (preferred)
MOZAL β€” 25–40 MW
Indicated interest only β€” no binding commitment at teaser stage
MOZAL Demand Note. MOZAL's indication of 25–40 MW demand is sourced from the MB_REN Consulting teaser and has not been independently verified or confirmed through a binding offtake letter or heads of terms. Investors must conduct direct due diligence with MOZAL's South32 management to determine: (1) whether the indicated demand is for firm baseload power or supplemental peaking/renewable power; (2) South32's corporate power purchasing policy and whether a direct-wire C&I PPA is permitted under Mozambican electricity regulation; and (3) MOZAL's current contracted power sources and any existing capacity constraints at the Beleluane substation.
Technical Specifications

PVSyst Preliminary Yield & Beleluane Grid Context

A preliminary PVSyst energy yield simulation (Version 7.4.8, JA Solar) has been completed for the 30 MWp fixed-tilt configuration at the Boane/Beleluane site. The geographical reference coordinates are Mabol, Mozambique (26.04Β°S, 32.31Β°E, altitude 12 m, UTC+2) β€” a coastal Meteonorm weather station using synthetic data from 1991–2011. The simulation models 48,000 PV modules at 30.00 MWp DC, connected to 74 inverters with a combined AC output of 25.90 MWac (DC/AC ratio 1.158). The array is fixed plane at tilt 20Β° / azimuth 0Β°. At latitude 26Β°S near Maputo, the tilt choice of 20Β° provides near-optimal annual yield for this coastal location, and the simulation annual GHI of 1,878 kWh/mΒ² is consistent with published World Bank/ESMAP solar resource data for the Maputo region.

PVSyst v7.4.8 β€” Preliminary Simulation β€” JA Solar / MB_REN Consulting
Boane β€” Energy Yield Summary
P50 Annual Yield
53,310 MWh
53,309,953 kWh/year
P90 Annual Yield
49,696 MWh
49,696,144 kWh/year
Specific Yield (P50)
1,777 kWh/kWp
Performance Ratio PR: 86.64%
P95 Annual Yield
48,679 MWh
48,679,359 kWh/year

The Boane project's P50 specific yield of 1,777 kWh/kWp/year is approximately 6% lower than the Alto Molocue figure (1,886 kWh/kWp/year). This difference is attributable to the lower altitude of the Beleluane/Maputo coastal site (12 m vs 625 m), higher ambient temperatures that reduce module efficiency, and the lower annual GHI at the 26Β°S latitude compared to ZambΓ©zia Province. The Maputo coastal environment also introduces higher humidity and salt aerosol soiling losses on module surfaces, though the preliminary simulation's standard synthetic weather data may not fully capture seasonal coastal variability. The P90/P50 ratio implies a yield at the 90th percentile confidence level approximately 6.8% below P50, consistent with a well-characterised irradiation climate.

System Configuration
Fixed-Tilt
Tilt 20Β° / Azimuth 0Β° β€” optimised for 26Β°S latitude
PV Modules
48,000 units
JA Solar β€” total DC 30.00 MWp
Inverters
74 units
AC output: 25.90 MWac β€” DC/AC ratio 1.158
Annual GHI
1,878 kWh/mΒ²
Mabol coastal reference β€” Meteonorm synthetic 1991–2011
Site Altitude
12 m asl
Coastal Maputo Province β€” humidity and soiling to be assessed
Grid Connection
66 kV β€” 6 km
Beleluane Substation β€” EDM Southern network
Beleluane Grid Capacity Note. The original Boane substation was found insufficient for 50 MW injection during EDM's grid integration studies. The Beleluane alternative substation is described as capable of accommodating the project, but no formal grid impact study result for 30 MW injection at Beleluane has been disclosed in the teaser. A grid connection agreement with EDM at Beleluane must be treated as a pending technical confirmation. If MOZAL is to receive power directly, the internal MOZAL substation metering and interconnection arrangements at Beleluane Industrial Park must also be evaluated.
Financial Structure

Dual-Path Revenue Strategy β€” EdM vs MOZAL

The Boane project faces a binary revenue structuring decision that fundamentally differentiates it from Alto Molocue and from a typical Mozambican IPP: the emergence of MOZAL as a potential industrial offtaker creates two distinct commercial pathways with materially different credit, tenor, and bankability profiles. The choice of offtake structure will determine the financing instruments available, the political risk mitigation requirements, and ultimately the achievable debt and equity terms.

Path A β€” EdM PPA (Baseline)

Under the EdM 20-year take-and-pay PPA structure (identical to Alto Molocue), revenue is EdM's CCC-rated utility obligation, requiring sovereign counter-guarantee from the Ministry of Finance and DFI credit enhancement. This path follows the precedent of existing Mozambican solar IPPs (Mocuba, Cuamba) and is politically well-supported under MIREME's mandate. No tariff has been disclosed. The financial model is pending negotiation with EdM and MoF.

Path B β€” MOZAL Industrial Offtake (Preferred)

A direct C&I PPA with MOZAL (operated by South32 as majority shareholder) would provide a substantially stronger corporate credit counterpart than EdM, potentially enabling commercial bank financing without DFI credit enhancement. MOZAL's indicated demand of 25–40 MW aligns almost entirely with the plant's nominal AC output of 25.90 MWac. However, solar PV is an intermittent resource and aluminium smelting requires continuous 24-hour power β€” making storage, hybrid configuration, or grid-backup provisions essential elements of any direct MOZAL offtake structure. Regulatory enablement (whether Mozambican law permits direct-wire C&I PPAs or requires routing through EDM) must be confirmed under the 2022 Electricity Law.

PPA Tariff (EdM)
Not disclosed
To be negotiated with EdM and MoF β€” key Financial Close condition
MOZAL Offtake Price
Not disclosed
Indication only β€” no binding commitment at teaser stage
Total CAPEX
Not provided
No independent cost estimate available at teaser stage
PPA Tenor (EdM baseline)
20 Years
Take-and-pay β€” standard Mozambican IPP framework
MOZAL Demand
25–40 MW
Indicated interest β€” covers substantially all plant AC output
Project Structure
BOOT
EdM equity ~5% indicated β€” to be agreed in commercial framework
[Non verificato] β€” No Financial Model or Tariff Available. As with Alto Molocue, no PPA tariff, CAPEX estimate, IRR, or financial model has been disclosed in the teaser. The MOZAL demand figure is an indication sourced from MB_REN Consulting's teaser documentation. Investors must independently verify MOZAL's willingness and ability to enter a direct PPA, confirm the regulatory framework for C&I direct PPAs in Mozambique under the 2022 Electricity Law, and obtain a binding term sheet from South32/MOZAL before structuring a co-development commitment. The CAPEX for a 30 MWp plant at this location should include a storage component assessment if MOZAL requires 24-hour firm supply.
Risk Assessment

Project Risk Profile

The Boane project shares the same sovereign and regulatory risks as Alto Molocue, but introduces a distinct and important risk-opportunity duality: the MOZAL industrial offtake potential significantly improves the credit quality of the offtake arrangement but introduces a new layer of commercial, technical, and regulatory uncertainty. The site relocation is also a material unresolved item. At this stage, development-phase risks predominate, with the key uncertainties centring on the MOZAL offtake structure, grid capacity at Beleluane, and the regulatory pathway for direct industrial supply.

Risk CategoryDescriptionRatingMitigation / Note
MOZAL Offtake β€” Indicative Only MOZAL's demand indication of 25–40 MW is non-binding. South32 management may not proceed with a direct PPA, or may require conditions (firm supply, storage, price floor) incompatible with a standard solar-only project economics. High β€” Unconfirmed Obtain binding heads of terms from South32/MOZAL before structuring commercial framework. Commission technical assessment of MOZAL's actual power procurement strategy and appetite for renewable intermittency.
MOZAL Offtake Credit (Positive Factor) If a binding MOZAL PPA is achieved, South32's investment-grade corporate credit profile fundamentally removes the EdM CCC offtaker risk and may enable commercial bank financing without DFI credit support. Positive Differentiator Structure commercial framework to prioritise MOZAL offtake. Consider hybrid EdM + MOZAL PPA to cover full plant output and provide fallback coverage.
Site Relocation β€” Award Validity The bilateral award was likely issued for the original Boane site. The EDM-recommended relocation to Beleluane may require formal acknowledgement from MIREME/ARENE β€” if not secured, the development right may be challenged. High β€” Unconfirmed Obtain written confirmation from MIREME and ARENE that the bilateral award remains valid for the relocated Beleluane site before committing to co-development framework.
Beleluane Grid Capacity While the original Boane substation was confirmed insufficient, the Beleluane substation's capacity for 30 MW injection has not yet been formally confirmed by a grid impact study. Medium Commission EDM grid impact study at Beleluane connection point as a priority. If MOZAL direct-wire is pursued, assess MOZAL's internal electrical infrastructure capacity.
C&I Direct Supply Regulatory Risk Mozambican electricity law may require all large-scale generation to be wheeled through EDM's network, preventing a direct C&I PPA structure. The 2022 Electricity Law expanded private participation but specific direct-wire provisions are unclear. Medium β€” Unconfirmed Obtain legal opinion from Mozambican electricity counsel on direct supply permissibility under Law 12/2022 before structuring MOZAL commercial framework.
Solar Intermittency vs MOZAL Baseload MOZAL aluminium smelting requires 24-hour continuous power. A solar-only plant provides only daytime generation, creating a structural mismatch unless storage, grid backup, or a hybrid arrangement is designed. Medium Assess whether MOZAL's requirement is for supplemental daytime renewable power (manageable) or firm baseload replacement (requires BESS or hybrid). Size storage component accordingly in CAPEX model.
Mozambique Sovereign Risk Same sovereign risk as Alto Molocue β€” ratings CCC+ (S&P) / CCC (Fitch) / Caa2 (Moody's). Southern Mozambique (Maputo Province) is more politically stable than northern provinces and closer to South African economic infrastructure. Medium Maputo Province location is a relative mitigant versus northern provinces. MIGA PRI still recommended for EdM-component revenue. MOZAL pathway reduces sovereign exposure if South32 PPA route is achievable.
EdM Offtaker Risk (fallback) If MOZAL offtake is not achievable, the project reverts to the EdM PPA route with the same CCC credit constraints as Alto Molocue, requiring DFI credit enhancement. High (if MOZAL fails) Maintain EdM PPA negotiations in parallel with MOZAL discussions. Do not structure the project as entirely dependent on MOZAL until a binding term sheet is in place.
Development Timeline

From Award to MOZAL/EdM Offtake β€” Critical Path

Completed
Site Identification & DUAT Secured β€” Boane Area
A 64-hectare site in the Boane Municipality, Maputo Province has been identified and secured through a DUAT under Land Law No. 19/97. Original planned connection: Boane Substation at 66 kV.
Completed
Bilateral Award β€” MIREME & ARENE Selection
Local developer selected by MIREME and ARENE for 30 MWp (up to 50 MWp) BOOT development via bilateral procurement. EdM designated as offtaker for 20-year take-and-pay PPA. EdM indicates potential 5% equity interest in Project Company.
Completed
MoU with EdM Signed
Memorandum of Understanding signed with Electricidade de MoΓ§ambique establishing the PPA negotiation framework.
Completed
Preliminary PVSyst Simulation
JA Solar has completed preliminary PVSyst v7.4.8 simulation for the 30 MWp fixed-tilt configuration. P50: 53,310 MWh/year; specific yield: 1,777 kWh/kWp/year; PR: 86.64%. Simulation uses Mabol synthetic weather station data (1991–2011).
Strategic Pivot β€” Completed
EDM Grid Studies β€” Boane Substation Insufficient β†’ Beleluane Recommended
⚑ EDM's National Power Grid Integration Studies have determined that the Boane Substation cannot accommodate the planned energy output. EDM has recommended relocating the project connection to the Beleluane Substation near MOZAL, 6 km from the site. This pivot introduces the MOZAL industrial offtake opportunity.
Current Stage
Co-Development Partner Identification & MOZAL Engagement
⏳ Two parallel tracks are required: (1) co-development partner identification via MB_REN Consulting mandate; (2) direct engagement with South32/MOZAL to determine whether the industrial offtake indication can be converted to a binding heads of terms. Both tracks are currently open. Studio Santi Capital supports investor engagement for this opportunity.
Next Step
Award Validity Confirmation & Beleluane Grid Impact Study
Written confirmation from MIREME/ARENE that the bilateral award applies to the relocated Beleluane connection. Formal grid impact study with EDM at the Beleluane 66 kV substation. Confirmation of available injection capacity and connection cost.
Parallel to Grid Studies
MOZAL Heads of Terms / EdM PPA Negotiation
If MOZAL pathway is pursued: engage South32 for binding power offtake heads of terms. If EdM pathway maintained: negotiate PPA terms, tariff, and MoF counter-guarantee simultaneously with grid studies. MAAP preliminary ESIA submission in parallel.
Financial Close
Debt & Equity Closing β€” Offtake Secured
Capital structure determined by offtake route: MOZAL pathway may enable commercial bank financing with reduced DFI requirements; EdM pathway requires DFI credit enhancement and MoF sovereign guarantee. EPC contractor selected with fixed-price, date-certain terms including any BESS component.
Construction & COD
30 MWp Commissioned at Beleluane β€” Revenue Commences
Commissioning and Commercial Operation Date. Power delivered to MOZAL and/or EDM Southern grid at Beleluane Substation (66 kV). BOOT period commences, plant operated by the IPP Project Company for PPA duration.

Engage as Co-Development Partner

The Boane project offers the MOZAL industrial offtake opportunity as a materially different credit structure from a standard EdM PPA. Site, DUAT, bilateral award, and preliminary PVSyst analysis are in place. Contact Studio Santi Capital to access the full MB_REN Consulting teaser and initiate engagement with the local developer and MB_REN.

Express Interest β†’
← See also Alto Molocue Solar Back to All Projects β†’